Client : GEOCEAN & SAPETRO
Dates : 2013 – 2014
Presentation :
- Republic of Benin
- CBM terminal for 10,000 DWT tankers and 70,000 DWT tankers
- Export line diameter: 20”
- Submarine hose length: 91 m
- Water depth: 20 m
- Distance to shore: 7 km
DVO Services :
CBM design including detailed engineering, risk assessment, method statement, technical specifications & data sheets for procurement, testing procedures, installation procedures, operation & maintenance manual for:
- Pipeline End Manifold (PLEM)
- Flexible hose lines
- Mooring buoys and their anchoring
- Navigational aids
- Mooring analysis
- Spare parts and consumables for commissioning and for 2 years operations
Onsite work:
- Assistance for the trenching operations
- Assistance for the onshore pipe laying
Supervision of the offshore campaign
Client: SONARA
Date: 2007-2009
Presentation :
- Cameroon, Limbé
- The Refinery jetty was seriously damaged during a tanker manoeuvre and required heavy structural repairs
DVO Services :
- Project management and client representative
- Planning of the works
- Engineering of a temporary CBM to receive tankers during the jetty repairs
- Supervision of the temporary CBM installation
- Supervision of the preparation of piles to be installed (50 m long, 1,85 m diameter, 80 tonnes)
- Supervision of the jetty repairs with the assistance of a jack-up barge. This included drilling for installation of 3 berthing dolphins, reinforcement of the jetty primary frame and installation of a 60 m long gangway.
Client : ICR for Total
Date : 2008
Presentation :
- Nigeria
- Import / export terminal for refined products
- Tanker size: from 10-15 000 DWT to 40 – 50 000 DWT
- Between 2 and 4 pipelines
DVO Services :
- Feasibility study
- Study of CBM / SPM and jetty options
- Positioning of the terminal
- Routing and sizing of the pipelines
Client : GEOCEAN and TOTAL
Dates : 2005
Presentation :
- Somaliland
- Pipeline laying project for refined products
- Installation of a new mooring system for product tankers in the bay of Berbera
DVO Services :
- Study for substituting the existing terminal with a submarine pipeline and a mooring system
- Study for dismantling the existing damaged offloading arms
- Engineering of the new mooring system
- Preparation and launch of the calls for tenders for the supply of material and for the operations
- Conceptual study for disassembling of the jetty and installation of the terminal
- On-site works engineer: organisation of the submarine pipeline and the CBM installations
Client : TOTAL
Dates : 2001 – 2002
Presentation :
- Equatorial Guinea
- Terminal receiving product tankers (gasoline, diesel oil , kerosene, ~100.000 tons per year)
- Offloading line: 6” and 400 m long floating hose
- Water depth: from 12 to 20 m
DVO Services :
- Inspection of the marine installations in the terminal
- Study of the different mooring and offloading alternatives (CBM, SPM, dolphins, jetty… and floating hose, subsea pipeline, aerial pipeline)
- Detailed design of the new terminal
- Preparation of the Engineering Procurement Construction and Installation contract for the 8” pipeline and the mooring buoy
Client : QATARGAS
Dates : 1992-1995
Presentation :
- North of Qatar
- Building of a LNG port to export gas from “North Field”
DVO Services :
- Port engineering for installation of loading facilities for tankers between 50 000 and 300 000 DWT
- Identification of port modifications necessary for receiving those tankers. Port simulations
- Feasibility study
- Assistance for port modifications
- Redaction of loading procedures